Piped storm water drainage — 500 m

Urban storm drain under a carriageway or footway: trench, 600mm pipeline, concrete surround, manholes and road gullies, discharging to a protected outfall.

Typical drawing: Piped storm water drainage — 500 m
What the bill measures
ItemQtyUnit
22.01(a)(i) Excavation for culverts: soft material, 0.5 m up to 1.5 m deep
500m x 1.2m x 1.5m average depth; split by depth band against the long section before issue
900 m3
22.02(b) Backfilling using imported selected material
selected backfill over pipe
700 m3
22.03(a) Concrete pipe culverts on Class A bedding, 600 mm dia, trunk line 500 m
22.03(b) Concrete pipe culverts on Class B bedding, 300 mm dia, gully connections
34 No. x 5m
yours to price
170 m
22.07(a) Cast in situ concrete in Class A bedding, screeds and encasing for pipes, including formwork, class 15/20 blinding 50 mm to trench bed
600 m2
30 m3
22.07(a) Cast in situ concrete in Class A bedding, screeds and encasing for pipes, including formwork, class 20/20 haunching and surround under carriageway 125 m3
22.17(a) Manholes complete, 1050 mm dia, standard depth 1.5 m
at 45m centres and at each junction
yours to price
17 No.
22.17(b) Catchpits complete, road gullies with grating
both kerb lines at 30m centres
yours to price
34 No.
22.17(d) Extra over 22.17(a) for manholes deeper than the standard depth, 1050 mm dia
6 No. in the lower reach averaging 2.0m deep
yours to price
3 m
22.S1 Special item: trench support and dewatering to pipe trenches, provisional
measure against the trial pits
yours to price
500 m
23.01(a) Concrete kerbing, precast, laid and bedded
channel to the gullies, both sides
1,000 m
23.05(a) Inlet, outlet, transition and similar structures (typical designs), masonry outfall headwalls 2 No.
25.01(c) Wired and grouted stone pitching, 150 mm, outfall apron 40 m2
26.04(a) Galvanised gabion boxes, 2 x 1 x 1 m boxes, filled and laced
12 boxes, scour protection to the receiving channel; m2 of exposed face, 2 m2 per box; confirm the basis
24 m2
31.01(b) Removal of topsoil
1.2m trench width x 500m x 150mm
90 m3

Preliminaries and the contractor's own obligations (Bills 1 and 9) are added to the project too, unpriced. Items the library has no rate for — manholes, catchpits, small-bore pipes, trench support, and the contractor's own obligations in Bills 1 and 9 — are measured in full and left at nil for you to price. On a tender you are issuing that is the correct form: the rate column is the question. On one you are pricing, those are the lines to put your own build-up against first.