Murram access road — 1 km
6m carriageway: clearing, formation, 150mm gravel wearing course, side drains and three culvert crossings.
What the bill measures
| Item | Qty | Unit |
|---|---|---|
| 21.01(a)(i) Excavation for open drains: soft material, 0.0 m up to 1.5 m deep
side drains both sides, 2000m x 0.63 m3/m
|
1,260 | m3 |
| 22.03(b) Concrete pipe culverts on Class B bedding, 600 mm dia
3 crossings x 8m
|
24 | m |
| 23.05(a) Inlet, outlet, transition and similar structures (typical designs), masonry culvert headwalls and wingwalls | 6 | No. |
| 23.05(a) Inlet, outlet, transition and similar structures (typical designs), masonry scour checks | 20 | No. |
| 31.01(a) Clearing and grubbing
8m corridor x 1km
|
0.8 | ha |
| 31.01(b) Removal of topsoil
6m formation x 1km x 150mm
|
900 | m3 |
| 35.06(a) Compaction of the 300 mm below formation level to 95% MDD (AASHTO T180)
6m x 1km x 300mm; shaping to formation included
|
1,800 | m3 |
| 41.01(a) Natural gravel class G20 for gravel wearing course
6m x 1km x 150mm; dust watering included
|
900 | m3 |
Preliminaries and the contractor's own obligations (Bills 1 and 9) are added to the project too, unpriced. Items the library has no rate for — manholes, catchpits, small-bore pipes, trench support, and the contractor's own obligations in Bills 1 and 9 — are measured in full and left at nil for you to price. On a tender you are issuing that is the correct form: the rate column is the question. On one you are pricing, those are the lines to put your own build-up against first.