Footway & kerbing, both sides — 1 km

2m paved walkway each side of a 1 km road: base, cabro, precast kerbs to both faces, gullies at the channel and marked crossings.

Typical drawing: Footway & kerbing, both sides — 1 km
What the bill measures
ItemQtyUnit
22.17(b) Catchpits complete, road gullies with grating
channel line at 30m centres
yours to price
34 No.
31.01(b) Removal of topsoil
2m x 2 sides x 1km x 150mm
600 m3
35.06(a) Compaction of the 300 mm below formation level to 95% MDD (AASHTO T180)
shaping to formation included
1,200 m3
35.12(a) Grassing, including topsoiling
verge behind the kerb
1,000 m2
62.01(a) Concrete kerbing, precast, laid and bedded
road face and back face, both sides
4,000 m
62.03(a) Concrete block paving, 60 mm blocks on sand bed 4,000 m2
62.S1 Special item: hand-packed stone base 200 mm under block paving 4,000 m2
85.01(a) Road marking paint: white lines, broken or unbroken, 100 mm wide
400m of line at crossings and channel edge
40 m2

Preliminaries and the contractor's own obligations (Bills 1 and 9) are added to the project too, unpriced. Items the library has no rate for — manholes, catchpits, small-bore pipes, trench support, and the contractor's own obligations in Bills 1 and 9 — are measured in full and left at nil for you to price. On a tender you are issuing that is the correct form: the rate column is the question. On one you are pricing, those are the lines to put your own build-up against first.