County / national tender
Roadside drainage, both sides — 1 km
Open lined side drains to a 1 km rural road: 2 km of drain excavated to profile, grouted stone pitching, scour checks, six culvert crossings and gabion outfalls.
What the bill measures
| Item | Qty | Unit |
|---|---|---|
| 21.01(a)(i) Excavation for open drains: soft material, 0.0 m up to 1.5 m deep
2000m x 0.63 m3/m
|
1,260 | m3 |
| 22.03(b) Concrete pipe culverts on Class B bedding, 600 mm dia
6 crossings x 8m
|
48 | m |
| 22.07(a) Cast in situ concrete in Class A bedding, screeds and encasing for pipes, including formwork, class 20/20, bedding and aprons | 9 | m3 |
| 23.05(a) Inlet, outlet, transition and similar structures (typical designs), masonry scour checks
at 50m centres on grade
|
40 | No. |
| 23.05(a) Inlet, outlet, transition and similar structures (typical designs), masonry culvert headwalls and wingwalls
inlet and outlet to each crossing
|
12 | No. |
| 25.01(c) Wired and grouted stone pitching, 150 mm, drain lining
2000m x 1.65 m2/m
|
3,300 | m2 |
| 25.01(c) Wired and grouted stone pitching, 150 mm, outfall aprons | 120 | m2 |
| 26.04(a) Galvanised gabion boxes, 2 x 1 x 1 m boxes, filled and laced
24 boxes at 6 outfalls; m2 of exposed face, 2 m2 per box; confirm the basis
|
48 | m2 |
| 31.01(a) Clearing and grubbing
1.5m working width x 2 sides x 1km
|
0.3 | ha |
| 35.12(a) Grassing, including topsoiling | 2,000 | m2 |
Preliminaries and the contractor's own obligations (Bills 1 and 9) are added to the project too, unpriced. Items the library has no rate for — manholes, catchpits, small-bore pipes, trench support, and the contractor's own obligations in Bills 1 and 9 — are measured in full and left at nil for you to price. On a tender you are issuing that is the correct form: the rate column is the question. On one you are pricing, those are the lines to put your own build-up against first.