Set two to four houses side by side at Nairobi rates, say what matters to you, and see which fits and how you could build it with the money you have. How this works

From your county planning office.
Your allowance for surprises.
Cost to own
0 adds costs up in today's prices.
What matters most to you?
Start again from my brief

The ranking

Best fit for what you said
1. 14-bedsitter block on an eighth acre
KES 12,701,163
14 bed · 3 storeys · 413.9 m² · score 100/100
    To own over 30 years: KES 14,447,960
    KES 1,746,797 in repaints and replacements, 3 parts with no figure yet. Year by year
    Try a variant
    Side by side
    1. 14-bedsitter block on an eighth acre
    HouseKES 11,706,173
    Plot works (walls, gate, driveway, septic)KES 994,990
    TotalKES 12,701,163
    With 10% contingencyKES 13,971,279
    Repaints and replacements over 30 yearsKES 1,746,797
    Cost to own over 30 yearsKES 14,447,960
    Per m² of floor (house)KES 28,283
    Floor area413.9 m²
    Roofed footprint139.1 m²
    Bedrooms · storeys14 · 3
    Build programme45 weeks
    Not priced yetnothing

    Building in stages

    Enter the cash you have now and what you can add each month, above, to see when each stage can start and when the house is finished.

    1. 14-bedsitter block on an eighth acre — KES 13,971,279
    StageCostWeeks StartsSaving firstTimeline
    Approvals, permits and setting up KES 800,998 1 not paid for on these savings
    Foundations to floor slab KES 808,671 10 not paid for on these savings
    Walling, frame and upper floors KES 4,102,241 10 not paid for on these savings
    Roof KES 1,074,606 9 not paid for on these savings
    Doors, windows and services KES 3,290,562 2 not paid for on these savings
    Finishes and fittings KES 2,799,712 13 not paid for on these savings
    External works KES 1,094,489 alongside not paid for on these savings
    Total incl. 10% contingency KES 13,971,279

    Not in these figures. Budget for these separately:

    • Professional fees: architect, structural engineer and quantity surveyor (get quotes through JengaCost's marketplace).
    • The land, and its search, survey and transfer costs.
    • Water and power connection fees.
    • Furniture, curtains and appliances.

    Figures are budget estimates from JengaCost's dated rate library adjusted to Nairobi, not quotations. The ranking is worked out from the priorities you set, not a judgement that one house is better. See questions and answers.