Cost to own: L-shaped 3-bedroom with veranda
What a house costs over its life: the build, then every repaint and replacement as it falls due, priced from the house's own bill, and your running bills. How this works
To build, with plot works
KES 4,726,883
Repaints and replacements
KES 508,671
8 jobs over 30 years
Running bills
—
Enter your monthly bills above
Cost to own over 30 years
KES 5,235,554
11% more than the build
Not in the figure, because there is no published interval or no rate yet:
Windows, Taps and cistern fittings, Septic tank desludging. The figure is a floor until these are known.
What falls due, year by year
| Year | Job | Cost today |
|---|---|---|
| 7 | Repaint outside walls (121 m²) | KES 38,704 |
| 10 | Repaint inside walls (277 m²) | KES 88,528 |
| 14 | Repaint outside walls (121 m²) | KES 38,704 |
| 20 | Replace fascia and gutters | KES 56,800 |
| Repaint inside walls (277 m²) | KES 88,528 | |
| Replace internal doors | KES 120,000 | |
| 21 | Repaint outside walls (121 m²) | KES 38,704 |
| 28 | Repaint outside walls (121 m²) | KES 38,704 |
How long each part lasts, and why we think so
The cost of each job is the house's own bill line at today's Nairobi rates. No Kenyan table of component lives was found, so lives come from manufacturers' warranties where they exist and otherwise from an American inspectors' chart, lower end of each range. Change any interval to your fundi's or QS's figure.