3-Bedroom Bungalow — preliminary concept

Standard finish · 100.8 m² plinth · all-in 26,525 KES/m²
← Change options
Preliminary concept — not for construction. Figures are budgeting estimates from the live rate library; quantities are template approximations. County approvals require drawings from a registered professional — see below.
Lounge5.4 × 3.9mBedroom 23.3 × 3.9mBedroom 33.3 × 3.9mCorridor6.6 × 1.2mKitchen2.7 × 4.5mDining2.7 × 4.5mBath2.0 × 1.6mWC2.0 × 1.7mMaster bedroom4.6 × 3.3m12.0 m8.4 m3-Bedroom Bungalow · 101 m²DRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFT — NOT FOR CONSTRUCTIONComputer-generated concept — dimensions and layout are indicative and have no structural design behind them.Structural drawings must be prepared and stamped by a registered Professional Engineer before building.Structural drawings: Ian Duncan Gichohi Waiguru · dwaiguru4@gmail.com
Draft elemental estimate (standard rates)
Element / itemUnit QtyRate Amount (KES)
Preliminaries & substructure 486,285.00
Site clearance & setting out m2 151.2 150.00 22,680.00
Strip foundation excavation (600 wide × 1000 deep) m3 30.5 650.00 19,825.00
Mass concrete 1:3:6 in foundation footing m3 4.6 16,500.00 75,900.00
Foundation walling to DPC level m2 45.8 2,200.00 100,760.00
Hardcore filling, compacted m2 100.8 450.00 45,360.00
Ground floor slab incl. mesh & DPM m2 100.8 2,200.00 221,760.00
Walling 426,330.00
Superstructure walling (machine-cut stone) m2 140.2 2,300.00 322,460.00
Ring beam incl. reinforcement LM 61.1 1,700.00 103,870.00
Roofing 383,765.00
Timber roof trusses & purlins m2 118.9 1,700.00 202,130.00
30g box profile roofing sheets m2 118.9 1,150.00 136,735.00
Fascia board & gutters LM 44.9 1,000.00 44,900.00
Doors & windows 211,600.00
Steel external door 900 × 2100 (D1) No. 2 22,000.00 44,000.00
Flush internal door 800 × 2100 (D2) No. 6 15,000.00 90,000.00
Steel casement windows incl. glazing m2 9.7 8,000.00 77,600.00
Finishes 568,248.00
Plaster to walls (both faces) m2 280.4 700.00 196,280.00
Floor screed m2 100.8 650.00 65,520.00
Ceramic floor tiling (wet areas + circulation) m2 25.2 2,600.00 65,520.00
Gypsum ceiling on brandering m2 100.8 1,500.00 151,200.00
Painting, 3 coats emulsion m2 280.4 320.00 89,728.00
Services 405,600.00
Plumbing - wet rooms complete Item 3 60,000.00 180,000.00
Electrical points (lighting & power) No. 27 2,800.00 75,600.00
Septic tank & soak pit Item 1 150,000.00 150,000.00
Approvals, levies & transport 191,922.00
County plan approval & building permit fees Item 1 30,240.00 30,240.00
NCA project registration levy (0.5% of works) Item 1 12,409.00 12,409.00
Materials transport to site Item 1 99,273.00 99,273.00
Temporary water & power for the works Item 1 50,000.00 50,000.00
Measured works total 2,673,750.00
Turn this into a working BOQ

Creates a project with every line above, linked to the rate library, ready to adjust to your site.

Start free to create the BOQ
Door & window schedule
RefTypeSize (mm)No.
D1Steel external door 900 × 21002
D2Flush internal door 800 × 21006
W1Steel casement 1200 × 12006
W2High-level louvre 600 × 6003
Finishes schedule
RoomFloorWallsCeiling
LoungeScreed (tiles optional) Plaster + emulsionGypsum, emulsion
Bedroom 2Screed (tiles optional) Plaster + emulsionGypsum, emulsion
Bedroom 3Screed (tiles optional) Plaster + emulsionGypsum, emulsion
CorridorScreed + tiles Plaster + emulsionGypsum, emulsion
KitchenCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
DiningScreed (tiles optional) Plaster + emulsionGypsum, emulsion
BathCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
WCCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
Master bedroomScreed (tiles optional) Plaster + emulsionGypsum, emulsion
Indicative programme (21 weeks)
StageWeeksTimeline
Mobilisation & site clearance1 wk 1–1
Substructure (foundations to slab)4 wk 2–5
Walling to ring beam4 wk 6–9
Roof structure & covering3 wk 10–12
Doors, windows & services first fix2 wk 13–14
Finishes (plaster, floors, ceilings, paint)5 wk 15–19
Fittings, second fix & snagging2 wk 20–21