2-Bedroom Bungalow — preliminary concept
Standard finish · 74.9 m² plinth ·
all-in 27,535 KES/m²
Preliminary concept — not for construction. Figures are
budgeting estimates from the live rate library; quantities are template
approximations. County approvals require drawings from a registered
professional — see below.
Draft elemental estimate (standard rates)
| Element / item | Unit | Qty | Rate | Amount (KES) |
|---|---|---|---|---|
| Preliminaries & substructure | 373,060.00 | |||
| Site clearance & setting out | m2 | 112.4 | 150.00 | 16,860.00 |
| Strip foundation excavation (600 wide × 1000 deep) | m3 | 24.5 | 650.00 | 15,925.00 |
| Mass concrete 1:3:6 in foundation footing | m3 | 3.7 | 16,500.00 | 61,050.00 |
| Foundation walling to DPC level | m2 | 36.7 | 2,200.00 | 80,740.00 |
| Hardcore filling, compacted | m2 | 74.9 | 450.00 | 33,705.00 |
| Ground floor slab incl. mesh & DPM | m2 | 74.9 | 2,200.00 | 164,780.00 |
| Walling | 326,120.00 | |||
| Superstructure walling (machine-cut stone) | m2 | 107.2 | 2,300.00 | 246,560.00 |
| Ring beam incl. reinforcement | LM | 46.8 | 1,700.00 | 79,560.00 |
| Roofing | 290,240.00 | |||
| Timber roof trusses & purlins | m2 | 88.4 | 1,700.00 | 150,280.00 |
| 30g box profile roofing sheets | m2 | 88.4 | 1,150.00 | 101,660.00 |
| Fascia board & gutters | LM | 38.3 | 1,000.00 | 38,300.00 |
| Doors & windows | 167,200.00 | |||
| Steel external door 900 × 2100 (D1) | No. | 2 | 22,000.00 | 44,000.00 |
| Flush internal door 800 × 2100 (D2) | No. | 4 | 15,000.00 | 60,000.00 |
| Steel casement windows incl. glazing | m2 | 7.9 | 8,000.00 | 63,200.00 |
| Finishes | 428,343.00 | |||
| Plaster to walls (both faces) | m2 | 214.4 | 700.00 | 150,080.00 |
| Floor screed | m2 | 74.9 | 650.00 | 48,685.00 |
| Ceramic floor tiling (wet areas + circulation) | m2 | 18.7 | 2,600.00 | 48,620.00 |
| Gypsum ceiling on brandering | m2 | 74.9 | 1,500.00 | 112,350.00 |
| Painting, 3 coats emulsion | m2 | 214.4 | 320.00 | 68,608.00 |
| Services | 328,800.00 | |||
| Plumbing - wet rooms complete | Item | 2 | 60,000.00 | 120,000.00 |
| Electrical points (lighting & power) | No. | 21 | 2,800.00 | 58,800.00 |
| Septic tank & soak pit | Item | 1 | 150,000.00 | 150,000.00 |
| Approvals, levies & transport | 148,590.00 | |||
| County plan approval & building permit fees | Item | 1 | 22,470.00 | 22,470.00 |
| NCA project registration levy (0.5% of works) | Item | 1 | 9,569.00 | 9,569.00 |
| Materials transport to site | Item | 1 | 76,551.00 | 76,551.00 |
| Temporary water & power for the works | Item | 1 | 40,000.00 | 40,000.00 |
| Measured works total | 2,062,353.00 | |||
Turn this into a working BOQ
Creates a project with every line above, linked to the rate library, ready to adjust to your site.
Door & window schedule
| Ref | Type | Size (mm) | No. |
|---|---|---|---|
| D1 | Steel external door | 900 × 2100 | 2 |
| D2 | Flush internal door | 800 × 2100 | 4 |
| W1 | Steel casement | 1200 × 1200 | 5 |
| W2 | High-level louvre | 600 × 600 | 2 |
Finishes schedule
| Room | Floor | Walls | Ceiling |
|---|---|---|---|
| Lounge | Screed (tiles optional) | Plaster + emulsion | Gypsum, emulsion |
| Kitchen | Ceramic tiles | Plaster + gloss (tile splash) | Gypsum, emulsion |
| Dining | Screed (tiles optional) | Plaster + emulsion | Gypsum, emulsion |
| Bedroom 1 | Screed (tiles optional) | Plaster + emulsion | Gypsum, emulsion |
| Corridor | Screed + tiles | Plaster + emulsion | Gypsum, emulsion |
| Bedroom 2 | Screed (tiles optional) | Plaster + emulsion | Gypsum, emulsion |
| Bath & WC | Ceramic tiles | Plaster + gloss (tile splash) | Gypsum, emulsion |
Indicative programme
(17 weeks)
| Stage | Weeks | Timeline |
|---|---|---|
| Mobilisation & site clearance | 1 | wk 1–1 |
| Substructure (foundations to slab) | 3 | wk 2–4 |
| Walling to ring beam | 3 | wk 5–7 |
| Roof structure & covering | 2 | wk 8–9 |
| Doors, windows & services first fix | 2 | wk 10–11 |
| Finishes (plaster, floors, ceilings, paint) | 4 | wk 12–15 |
| Fittings, second fix & snagging | 2 | wk 16–17 |
Advertisement
Ready to build this?
Ian Duncan Gichohi Waiguru —
Graduate civil engineer · concept design, drafting, 3D visualisation & take-offs.
Email Ian