1-Bedroom Bungalow — preliminary concept

Standard finish · 43.2 m² plinth · all-in 33,767 KES/m²
← Change options
Preliminary concept — not for construction. Figures are budgeting estimates from the live rate library; quantities are template approximations. County approvals require drawings from a registered professional — see below.
Lounge4.2 × 3.6mKitchen4.2 × 2.4mBedroom3.0 × 3.6mBath1.5 × 2.4mWC1.5 × 2.4m7.2 m6.0 m1-Bedroom Bungalow · 43 m²DRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFTDRAFT — NOT FOR CONSTRUCTIONComputer-generated concept — dimensions and layout are indicative and have no structural design behind them.Structural drawings must be prepared and stamped by a registered Professional Engineer before building.Structural drawings: Ian Duncan Gichohi Waiguru · dwaiguru4@gmail.com
Draft elemental estimate (standard rates)
Element / itemUnit QtyRate Amount (KES)
Preliminaries & substructure 230,800.00
Site clearance & setting out m2 64.8 150.00 9,720.00
Strip foundation excavation (600 wide × 1000 deep) m3 16.6 650.00 10,790.00
Mass concrete 1:3:6 in foundation footing m3 2.5 16,500.00 41,250.00
Foundation walling to DPC level m2 24.8 2,200.00 54,560.00
Hardcore filling, compacted m2 43.2 450.00 19,440.00
Ground floor slab incl. mesh & DPM m2 43.2 2,200.00 95,040.00
Walling 193,630.00
Superstructure walling (machine-cut stone) m2 62.9 2,300.00 144,670.00
Ring beam incl. reinforcement LM 28.8 1,700.00 48,960.00
Roofing 174,350.00
Timber roof trusses & purlins m2 51.0 1,700.00 86,700.00
30g box profile roofing sheets m2 51.0 1,150.00 58,650.00
Fascia board & gutters LM 29.0 1,000.00 29,000.00
Doors & windows 125,200.00
Steel external door 900 × 2100 (D1) No. 1 22,000.00 22,000.00
Flush internal door 800 × 2100 (D2) No. 4 15,000.00 60,000.00
Steel casement windows incl. glazing m2 5.4 8,000.00 43,200.00
Finishes 249,276.00
Plaster to walls (both faces) m2 125.8 700.00 88,060.00
Floor screed m2 43.2 650.00 28,080.00
Ceramic floor tiling (wet areas + circulation) m2 10.8 2,600.00 28,080.00
Gypsum ceiling on brandering m2 43.2 1,500.00 64,800.00
Painting, 3 coats emulsion m2 125.8 320.00 40,256.00
Services 372,000.00
Plumbing - wet rooms complete Item 3 60,000.00 180,000.00
Electrical points (lighting & power) No. 15 2,800.00 42,000.00
Septic tank & soak pit Item 1 150,000.00 150,000.00
Approvals, levies & transport 113,496.00
County plan approval & building permit fees Item 1 12,960.00 12,960.00
NCA project registration levy (0.5% of works) Item 1 6,726.00 6,726.00
Materials transport to site Item 1 53,810.00 53,810.00
Temporary water & power for the works Item 1 40,000.00 40,000.00
Measured works total 1,458,752.00
Turn this into a working BOQ

Creates a project with every line above, linked to the rate library, ready to adjust to your site.

Start free to create the BOQ
Door & window schedule
RefTypeSize (mm)No.
D1Steel external door 900 × 21001
D2Flush internal door 800 × 21004
W1Steel casement 1200 × 12003
W2High-level louvre 600 × 6003
Finishes schedule
RoomFloorWallsCeiling
LoungeScreed (tiles optional) Plaster + emulsionGypsum, emulsion
KitchenCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
BedroomScreed (tiles optional) Plaster + emulsionGypsum, emulsion
BathCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
WCCeramic tiles Plaster + gloss (tile splash)Gypsum, emulsion
Indicative programme (17 weeks)
StageWeeksTimeline
Mobilisation & site clearance1 wk 1–1
Substructure (foundations to slab)3 wk 2–4
Walling to ring beam3 wk 5–7
Roof structure & covering2 wk 8–9
Doors, windows & services first fix2 wk 10–11
Finishes (plaster, floors, ceilings, paint)4 wk 12–15
Fittings, second fix & snagging2 wk 16–17